     County Road 27, Bear Creek Hydraulic Improvements, County of Simcoe

    PEARSON ENGINEERING LTD. was retained to complete the detailed design for hydraulic improvements of Bear Creek at County Road 27. Detailed design of 4 sets of twin concrete box culverts up to 2.4m x 1.2m were required to convey the 50 year peak flow from Bear Creek under the Barrie Collingwood Railway and County Road 27. Hydraulic modeling using HEC-RAS was completed to ensure the 50-year storm floodlines did not overtop County Road 27. Engineering services included design of site services, including parking lot, grading, water and sanitary service connections. A detailed Stormwater Management analysis and report were also completed.