About this Project
In addition to the Forest Heights subdivision in Oro-Medonte, PEARSON Engineering was engaged to complete further design and inspection works associated with Line 6 and the Horseshoe Valley Road right turn lane extension and realignment.
Services performed
- Detailed Grading Design
- Inspection
Key takeaways
- Closing the existing Line 6 intersection
- 180m Right Turning Lane Extension
- Shoulder Widening